Waterside Park

waterside_park_400_03.jpg

Having worked with this client on several previous occasions,
Lowe & Oliver was given the task of providing a new electrical
system for this building that would be flexible enough for
use by most businesses.

We installed a lighting layout to the office area, using the latest
LG3 light fittings, and provided a complete three-compartment
trunking system. Switch sockets were fitted and connected along
with containment, ready for future tenants to install data
systems. Lighting and power systems to all other parts of the
building were upgraded and a new fire system installed.

 

Keyfacts

Client: Highcross, Newbury 

Main contractor: Lowe & Oliver 

Value: £40,000

Start date: April 05

Completion date: June 05